Bug Parade Engage 0.1 Update 38

Colin Clark colinbdclark at gmail.com
Fri Oct 16 22:47:34 UTC 2009


We're in the home stretch now for freezing Engage 0.1. At this point,  
I think we just need confirmation on a few issues and then we're ready  
to go. I've added notes below with questions about the status of the  
remaining open issues.

Needs review:
EVERYTHING--let's schedule time for a group code review on Monday


Engage 0.1 Bug Parade
===================

General:

Blocker

FLUID-3208
Code Clean up
http://issues.fluidproject.org/browse/FLUID-3208
  * Anything else left to clean up, or are we good?

ENGAGE-88
Create the directory structure for the Engage 0.1 release and move the  
relevant pieces from the incubator
http://issues.fluidproject.org/browse/ENGAGE-88
  * Are we going to move Engage out of the incubator before or after  
we release? Other than that, the directory structure is all in place.


ENGAGE-95
Create Engage build scripts
http://issues.fluidproject.org/browse/ENGAGE-95
  * This is looking pretty good. Any last tasks still to do?


Major

ENGAGE-70
The fluid-all externals are named ambiguously and the Eclipse projects  
for engage-server and engage-client are incorrectly named
http://issues.fluidproject.org/browse/ENGAGE-70
  * We renamed "engage" to "engage-core," but we still need to rename  
"infusion" and "kettle"

---
Colin Clark
Technical Lead, Fluid Project
http://fluidproject.org