Here's the UX team plan for the current iteration, which runs until
April 28th. With the impending release of Fluid Infusion 0.3, we've
got lots on our plate at the moment. We're focussing on blockers for
the release in this iteration.
Here's the list of JIRA tasks:
http://issues.fluidproject.org/secure/IssueNavigator.jspa?mode=hide&requestId=10040
And the planning spreadsheet, which represents the critical path
leading up to Infusion 0.3 and the JA-SIG uCamp in St. Paul's:
http://spreadsheets.google.com/pub?key=py52-xhVHH6en0Aa7yl-eSQ
I've left several additional tasks related to the Open Source Design
Patterns Library in the JIRA filter, since there is some activity
going on this area on the side, thanks to Allison and Jonathan.
Let me know if you have any questions,